May 02- May 22, 2025
The procurement of the inverter is underway, so the plant will continue to be offline from May 2nd to 22nd. Forecasted credits for this period will be dispatched on April 30th. by 8pm. (6:50 pm, 30th Apr)
Issue Identified
Due to a fault with the existing inverter at the project site, it will be replaced with a new one. The order has already been placed, and for safety reasons, the inverter has been switched off for the next 20 days until the replacement is completed. (5:00 pm, 11th Apr)
Apr 11 - May 01, 2025
Issue Identified
Due to a fault with the existing inverter at the project site, it will be replaced with a new one. The order has already been placed, and for safety reasons, the inverter has been switched off for the next 20 days until the replacement is completed. (5:00 pm, 11th Apr)